Thursday, October 26, 2017

Construction Update
Cabot Danville US 2 Reconstruction
FEGC F 028-3(26) C/2
    
Project Location:  The 1.4 mile project extends along US 2 from Last Road to Danville Hill Road in Cabot. This is a multi-year project with most of the work occurring in 2017/2018. Completion is scheduled for 2019.

Expect traffic delays this week!  Traffic may be shifted to the new roadway alignment by the end of the week.

 
Week of October 30th, 2017
US 2 – East (Danville Side) of Goodrich’s Maple Farm
  Crews are scheduled to pave the newly reconstructed area behind the barrier this week. Following paving, new guardrail and line striping will be installed.

By the end of the week, traffic may be shifted to the new roadway alignment.

Alternating one-way traffic will be maintained for a construction package east of Goodrich’s Maple Farm.  Expect short delays.





 

US 2 Bridge #88 (Near Folsom Farm) Replacement:  
Crews will be backfilling abutments.  Traffic impacts will be minimal at this construction operation.

Traffic – Minor traffic delays can be expected this week.

It is illegal in VT to use any handheld portable electronic devices while driving. The law carries fines of up to $200 with points assessed if the violation occurs in a work zone. 

Contact Francine Perkins, Project Outreach Coordinator, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994.  Construction updates are posted at www.roadworkupdates.com

 