Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)

WEEK OF 5/6/13
Box cutting is complete!  Crews will now move onto fine grading and paving the base layer of asphalt.
Crews will start out the week fine grading the box cut roadway in anticipation of paving.  This work is scheduled for Monday through Wednesday.
Paving over the box cut areas is scheduled for later in the week and should take a few days. 
Two-way traffic will be maintained as much as possible.  However, Route 2 may be reduced to alternating one-way traffic in the center of Town at various times during the week.  Motorists should expect and plan for traffic delays when traveling in and around the project.
Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.