Work
Update
Danville
Route 2 Project
Project: Danville FEGC
028-3(32)
WEEK
OF 5/6/13
Box
cutting is complete! Crews will now
move onto fine grading and paving the base layer of
asphalt.
Crews
will start out the week fine grading the box cut roadway in anticipation of
paving. This work is scheduled for
Monday through Wednesday.
Paving
over the box cut areas is scheduled for later in the week and should take a few
days.
Two-way
traffic will be maintained as much as possible. However, Route 2 may be reduced to alternating
one-way traffic in the center of Town at various times during the week. Motorists should expect and plan for
traffic delays when traveling in and around the project.
Contact
Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any
questions or concerns with regard to this project at 802-479-6994 or for a more
up to date schedule visit www.roadworkupdates.com.