Project Update 5/02/19, Cabot-Danville US 2 Reconstruction [Cabot-Danville FEGC F 028-3(36) C/2] 

Project Location:  The 1.4 mile project extends along US 2 from Last Road to Danville Hill Road in Cabot. This is a multi-year project with most of the work occurring in 2017/2018. Completion is scheduled for 2019.


TRAVEL ALERT:  The speed reduction zone of 40 mph has been placed back in effect. Motorists should be advised that fines are doubled for exceeding the posted speed limit within the construction zone.
 

GRADING: Fine grading of the road will continue next week from Last Rd. to Goodrich’s Maple Farm. Motorists will encounter flaggers and a one-lane alternating traffic pattern. Please add a few extra minutes to your travel time as minor delays may occur.

DITCHING: Ditch and slope work will take place next week near Goodrich's.

PAVING: Paving is scheduled to begin mid-week next week, weather and conditions permitting.


Please focus on safety when driving through the construction work zone and remember, it is against the law to use a hand held cell phone while driving in Vermont.

Contact Natalie Boyle, Public Information Consultant, EIV Technical Services, with any questions or concerns in regard to this project at 802-855-3893 or 
nboyle@eivtech.com  

--
Natalie Boyle
Public Information Consultant

o.   (802) 497-3653 x1037   |    c.   (802) 855-3893    |    e.   nboyle@eivtech.com     |     w.  eivtech.com

No comments:

Spring Mix!

I started this a couple days ago but got kind of busy and never got back to it. I had posted about the Route 2 construction, but that notice...