Thursday, October 11, 2018

Proposed Work Schedule, Week of 10/15/18, Cabot-Danville US 2 Reconstruction [Cabot-Danville FEGC F 028-3(36) C/2] 

Project Location: 
 The 1.4 mile project extends along US 2 from Last Road to Danville Hill Road in Cabot. This is a multi-year project with most of the work occurring in 2017/2018. Completion is scheduled for 2019.

Crews have completed the road cut working toward Houghton Road. Underdrain installation in this location has been completed as well. 

Slope and ditch work from the Goodrich property back towards Houghton Rd. will continue next week. 

Work on driveways will continue.

Side road work will continue at Houghton Rd. 


Excavation at Last Road will take place next week.

TRAVEL ALERT:  A speed reduction zone of 40 mph is in place for this project. There are increased fines for speed violations within the construction zone. 

TRAFFIC INFORMATION: Construction vehicles will be entering and exiting the work zone throughout construction hours, and as a result, alternating one-way traffic patterns with flaggers will be in place. Delays can be expected.
 
Please focus on safety when driving through the construction work zone and remember, it is against the law to use a hand held cell phone while driving in Vermont.
Contact Natalie Boyle, Project Outreach Coordinator, EIV Technical Services, with any questions or concerns in regard to this project at 802-855-3893 or nboyle@eivtech.com

--
Natalie Boyle
Director of Communications

EIV Technical Services
The City Lights Building
106 East Allen St., Unit 506
Winooski, VT 05404

cell:  802.855.3893
office: 802.497.3653 ext.1037