Construction Update
Cabot Danville US 2 Reconstruction
FEGC F 028-3(26) C/2
  
Project Location:  The 1.4 mile project extends along US 2 from Last Road to Danville Hill Road in Cabot. This is a multi-year project with most of the work occurring in 2017/2018. Completion is scheduled for 2019.

Reduced Speed Limit – The posted speed limit has been reduced to 40 mph within the project limits.  Please reduce speed and use caution when traveling through the project.  Law enforcement may be present to patrol for speed enforcement.

Expect traffic delays this week!

 
Week of October 23rd, 2017
US 2 – East (Danville Side) of Goodrich’s Maple Farm
 
Crews will excavate to tie-in the newly reconstructed section of US 2 to the existing roadway.

Traffic will be shifted to use the widened area in front of Goodrich Maple Farm to maintain mobility through the project.
Alternating one-way traffic will be maintained for a construction package east of Goodrich’s Maple Farm.  Expect short delays.

US 2 Bridge #88 (Near Folsom Farm) Replacement:  
Crews will be removing the forms from the abutment walls and backfilling.  Crane pads will also be constructed to prepare for setting of the pre-cast bridge beams.  Traffic impacts will be minimal at this construction operation.

Traffic – Minor traffic delays can be expected this week.

It is illegal in VT to use any handheld portable electronic devices while driving. The law carries fines of up to $200 with points assessed if the violation occurs in a work zone. 

Contact Francine Perkins, Project Outreach Coordinator, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994.  Construction updates are posted at www.roadworkupdates.com