Thursday, August 31, 2017

Construction Update
Cabot Danville US 2 Reconstruction
FEGC F 028-3(26) C/2
    
Project Location:  The 1.4 mile project extends along US 2 from Last Road to Danville Hill Road in Cabot. This is a multi-year project with most of the work occurring in 2017/2018. Completion is scheduled for 2019.

Reduced Speed Limit – The posted speed limit has been reduced to 40 mph through the project.  Please reduce speed and use caution traveling through the construction zone.

Labor Day Holiday Weekend – In observance of Labor Day, no work will be performed on the project from 12:00 pm (Noon), Friday, September 1st, 2017 through Monday, September 4th, 2017.  Work will resume on Tuesday, September 5th, 2017.

 
Week of September 4th, 2017

Crews began excavating to widen the south side of US 2 just east of Goodrich’s Sugar House.  This work will continue this week and weather permitting, will be paved and line striped.

Traffic Shift - By the end of the week, the US 2 traffic pattern will shift traffic to use the newly widened section of the project. Following the traffic shift, crews will begin reconstruction of the north side of US 2 east of Goodrich’s Sugar House.

Traffic – Traffic delays can be expected this week.

It is illegal in VT to use any handheld portable electronic devices while driving. The law carries fines of up to $200 with points assessed if the violation occurs in a work zone. 

Contact Francine Perkins, Project Outreach Coordinator, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994.  Construction updates are posted at www.roadworkupdates.com