Friday, October 18, 2013

Finishing Touches to the Danville Route 2 Project

 

Punch List Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)


Crews will return to the project for the next couple of weeks to complete punch list items.


Week of 10/21/13 – Crews will be working on grinding sidewalk edges at crosswalk locations at Route 2/Hill Street/Peacham as well as at all traffic islands.  Landscapers will also be working on punch list items in various areas around the Village Green and the Library.  Traffic can expect to be interrupted with alternating one-way traffic while this work is being performed.  Crews will maintain two-way traffic as much as possible.

Week of 10/28/13 – New crosswalks will be installed on Park Street near the Post Office throughout the week.  Most likely, motorists can expect alternating one-way traffic around the work zone while crews perform this work. 

Other miscellaneous minor work will be performed throughout the project for the next few weeks in an effort to address the punch list items.

Contact Alex Sellar with Pike Industries with any questions or concerns with regard to this project at 603-630-9500.

No comments:

Regulations and Seasonal Changes

 The change to Vermont's boating regulations regarding wake boats went into effect on April 15. One of the new regulations I wasn't...