Punch
List Work Update
Danville
Route 2 Project
Project: Danville FEGC
028-3(32)
Crews
will return to the project for the next couple of weeks to complete punch list
items.
Week
of 10/21/13 – Crews
will be working on grinding sidewalk edges at crosswalk locations at Route
2/Hill Street/Peacham as well as at all traffic islands. Landscapers will also be working on
punch list items in various areas around the Village Green and the Library. Traffic can expect to be interrupted
with alternating one-way traffic while this work is being performed. Crews will maintain two-way traffic as
much as possible.
Week
of 10/28/13 – New
crosswalks will be installed on Park Street near the Post Office throughout the
week. Most likely, motorists can
expect alternating one-way traffic around the work zone while crews perform this
work.
Other
miscellaneous minor work will be performed throughout the project for the next
few weeks in an effort to address the punch list items.
Contact
Alex Sellar with Pike Industries with any questions or concerns with regard to
this project at 603-630-9500.