Danville Route 2 Project
Project:  Danville FEGC 028-3(32)

WEEK OF 8/12/13

Mark your calendars!  Fair-Well PIKE Event - Saturday, August 10th, 2013, Hill Street Park in Danville.  Get more details on Fair-Well PIKE’s Facebook page!  Looks like it will be loads of fun!!!

Work this week will include:
  • Work on the drip edge of the Bandstand in the Village Green was postponed last week.  Work is expected to occur Monday/Tuesday this week.
  • Sidewalk work will begin on Monday and continue through the week on Park Street to the Library and also around the Bandstand.
  • Crews will be installing concrete steps at a residence on Route 2 next to the Diamond Hill Store.  This work will require alternating one-way traffic at various times later in the week when the concrete is being poured. 

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Catching Up

 As our lovely autumn days begin to turn a bit chill and dreary - the transition from October to November is like that  - I want to share so...