Work
Update
Danville
Route 2 Project
Project: Danville FEGC
028-3(32)
WEEK
OF 7/1/13
In
observance of Independence Day, crews will not be performing any work on the
project Thursday, July 4th and Friday July 5th. Work will resume on Monday, July
8th.
PAVING:
The
majority of the final wearing course paving is complete!!!!
Crews
still have to finish up paving driveway entrances around the Village Green,
Route 2 and Hill Street. They are
planning to pave these areas Tuesday, if the weather
cooperates.
LINE
STRIPING: Crews
will be out preparing the newly paved roadway for line stripes.
Miscellaneous
clean-up work will be performed throughout the week.
Travel
will be reduced to alternating one-way traffic while most of the work above is
being performed. Motorists should expect and plan for
traffic delays when traveling in and around the project.
Contact
Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any
questions or concerns with regard to this project at 802-479-6994 or for a more
up to date schedule visit www.roadworkupdates.com.