Friday, November 02, 2012

Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)
 WEEK OF 11/5/12

Village Green:

UTILITY CREWS – Crews from FairPoint and Charter will be working for the next few months to relocate their lines underground. 

 Route 2:

Street Lights:  GMP crews will be energizing the new street lighting on Route 2.

Tuesday, crews will be sealing structures along Route 2, weather permitting.   This work will require alternating one-way traffic around the work zone.  Traffic control will be present to maintain traffic flow.

Miscellaneous clean-up activities will take place in anticipation of the project winter shut-down.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Another Adventure

This week turned out to be a doozie for me. I had anticipated going for a follow-up on my knee on Monday, but instead ended up in the ER at ...