Work
Update
Danville
Route 2 Project
Project: Danville FEGC
028-3(32)
WEEK
OF 11/5/12
Village
Green:
UTILITY
CREWS – Crews from FairPoint and Charter will be working for the next few months
to relocate their lines underground.
Route
2:
Street
Lights: GMP crews will be
energizing the new street lighting on Route 2.
Tuesday,
crews will be sealing structures along Route 2, weather permitting. This work will require alternating
one-way traffic around the work zone.
Traffic control will be present to maintain traffic
flow.
Miscellaneous
clean-up activities will take place in anticipation of the project winter
shut-down.
Contact
Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any
questions or concerns with regard to this project at 802-479-6994 or for a more
up to date schedule visit www.roadworkupdates.com.