Project: Danville FEGC
028-3(32)
WEEK
OF 10/1/12
Village
Green:
UTILITY
CREWS – Crews from FairPoint and Charter will be working for the next few months
to relocate their lines underground.
Route
2:
PAVING: Weather permitting, crews will be paving
all day Sunday 9/30/12 through midnight-12:00 am. If it rains and the shift is cancelled
on Sunday, 9/30/12– crews will work Monday, October 1st from 6:00 pm
to 6:00 am.
The
plan for paving is for is to start at the west end of the project and head east
towards Marty’s. Paving of Route 2
will also include paving in the side road entrances for Highland Ave, Mountain
View Drive and Walden Hill Road.
Motorists
can expect alternating one-way traffic through the construction zone. Traffic control personnel will be
present to maintain traffic flow.
DRIVEWAY
APRON PAVING: During daytime work
hours, crews will be paving in driveway aprons throughout the week. This work is dependent on favorable
weather conditions.
Following
paving, crews will be placing shoulder material along the project. Line striping crews will also be
grinding the new pavement for final line striping.
Contact
Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any
questions or concerns with regard to this project at 802-479-6994 or for a more
up to date schedule visit www.roadworkupdates.com.