Project: Danville FEGC
028-3(32)
WEEK
OF 5/21/12
Utility
Duct Bank Installation UPDATE:
Utility
duct bank installation is complete!
This work was not scheduled to be completed until the end of June but
with the patience and cooperation of the Danville community along with the hard
work of the crews, this work was completed over a month early! Utility companies can now begin
relocating lines underground.
Utility
Work:
Utility
crews will begin relocating the utility lines on Route 2 near Melody Hill Farm
and Passumpsic Bank.
Tuesday,
travel will be reduced to alternating one-way traffic near Melody Hill
Farm.
Route
2 Roadwork:
Crews
will continue to focus on the west end of the project with fine grading the
roadway in preparation for installation of the base layer of pavement by mid to
late week. Grading and paving
operations will require alternating one-way travel around the construction
package.
Paving
operations are weather dependent.
Unfavorable weather conditions could postpone paving to a later
date.
Contact
Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any
questions or concerns with regard to this project at 802-479-6994 or for a more
up to date schedule visit www.roadworkupdates.com.