Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)

WEEK OF 5/21/12
Utility Duct Bank Installation UPDATE:

Utility duct bank installation is complete!  This work was not scheduled to be completed until the end of June but with the patience and cooperation of the Danville community along with the hard work of the crews, this work was completed over a month early!  Utility companies can now begin relocating lines underground. 

Utility Work:

Utility crews will begin relocating the utility lines on Route 2 near Melody Hill Farm and Passumpsic Bank.

Tuesday, travel will be reduced to alternating one-way traffic near Melody Hill Farm. 

Route 2 Roadwork:

Crews will continue to focus on the west end of the project with fine grading the roadway in preparation for installation of the base layer of pavement by mid to late week.  Grading and paving operations will require alternating one-way travel around the construction package.

Paving operations are weather dependent.  Unfavorable weather conditions could postpone paving to a later date. 

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.