Friday, April 20, 2012

Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)

WEEK OF 4/23/12
The work plan for Route 2 this week will have crews concentrating on the West end of the project between the Danville School and the end of the project. 
Crews will continue installing drainage pipe at Walden Hill Road and work their way west. This work will require alternating one-way traffic around the work zone.
Duct bank work will continue on Park Street and then crews will move onto Peacham Road.  Like last week, access to these streets may be temporarily interrupted.  Motorists will be re-directed to alternate routes around the Green and all businesses around the Green will be accessible while this work occurs.
Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.