Thursday, April 26, 2012

DANVILLE ROUTE 2 PROJECT
REVISED VILLAGE GREEN STREET CLOSURE
FOR FRIDAY, APRIL 27, 2012

Friday, crews will continue to install utility duct banks at the corner of Peacham Road and Park Street near the Danville Post Office.  Peacham Road between Route 2 and Park Street is reduced to alternating one-way traffic.  Access to the Post Office from Peacham Road is closed due to the excavation. Motorists who are going to the Danville Post Office from Route 2 will need to use Smith Street. 

Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)

WEEK OF 4/30/12
The work plan for Route 2 this week will have crews concentrating on the West end of the project between the Danville School and the end of the project. 
Crews will continue installing drainage pipe at Walden Hill Road and work their way west. This work will require alternating one-way traffic around the work zone.
Village Green Street Closures-
Monday, April 30th - Peacham Road will be closed from Route 2 to Park Street while crews excavate across Peacham Road.  Motorists are encouraged to use Smith Street and Park Street as alternate Routes around the Green. 
For the next few weeks while crews are installing utility duct banks, the streets around the Village Green will intermittently close as crews work their way across the area.  Daily traffic alerts will be issued to the public and posted on www.roadworkupdates.com by late afternoon of each day as to the closures scheduled for the following day.  Motorists will be re-directed to alternate routes around the Green and all businesses around the Green will be accessible while this work occurs.
Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Update & Request

 Marti Talbot, Carolyn Hamilton's sister-in-law, emailed me this morning to thank everyone who has reached out to Carolyn while she'...