WEEK OF 11/7/11

DAY WORK:

WATER LINE SERVICES- work on water services will continue along Route 2 between Smith Street and the Danville School throughout the week.

STORM DRAIN – Crews will work on storm drain in and around the Village Green.

ROAD WORK – In anticipation of paving Route 2, crews will be grading the roadway between Park Street and the Danville School. Crews will also be adjusting the height of catch basins so they will match the height of the new pavement.

PAVING – Wednesday through Friday, crews are scheduled to pave along Route 2 from Marty’s to the Danville School. Paving of the roadway is contingent upon favorable weather conditions.

Motorists can expect traffic delays from the alternating one-way traffic around the construction zone. Traffic control will be present to maintain traffic flow. Motorists are encouraged to plan accordingly for delays.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Another Adventure

This week turned out to be a doozie for me. I had anticipated going for a follow-up on my knee on Monday, but instead ended up in the ER at ...