Here's a report of what to expect from the Rte. 2 construction project:
Work Update
Danville Route 2 Project
Project: Danville FEGC 028-3(32)
Week of May 16th, 2011
Pike Industries will be performing the following work on the Danville Route 2 project as follows:
Crews are scheduled to begin building a new sediment pond across from Marty’s Store. This work will have minimal impact, if any, on traffic flow.
Crews will also be cutting trees around the green. This work should have no impact on traffic.
Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.