Thursday, August 16, 2018

Proposed Work Schedule, Week of 8/20/18, Cabot-Danville US 2 Reconstruction [Cabot-Danville FEGC F 028-3(36) C/2]

Project Location:  The 1.4 mile project extends along US 2 from Last Road to Danville Hill Road in Cabot. This is a multi-year project with most of the work occurring in 2017/2018. Completion is scheduled for 2019.

Work to be performed includes reconstruction, realignment and widening of a portion of US Route 2 including bridge replacement, grading, drainage, sub-base, pavement and other highway related items.

Traffic pattern change and speed reduction to 35 mph from Last Road to Folsom Farm is in effect. Traffic will be using the temporary bridge that was previously installed.



Roadwork will continue from the Goodrich property to Folsom Farm.  Motorists are advised that a new traffic pattern is in place from the Folsom Farm to the Goodrich property. 

Bridge work will continue between Last Rd. and Houghton Road. 

Crews are tentatively scheduled to begin road work at the intersection of Last Road and Route 2. This work will progress westerly.


 TRAVEL ALERT: Motorists are advised that a traffic pattern change will be in effect at the temporary bridge, and the existing bridge will be closed. A speed limit reduction to 35 mph will be in effect at the location of the temporary bridge. The remainder of the project remains at the 40 mph speed reduction. There are increased fines for speed violations within the construction zone.

TRAFFIC INFORMATION: Construction vehicles will be entering and exiting the work zone throughout construction hours, and as a result, alternating one-way traffic patterns with flaggers will be in place. Brief delays can be expected.
 
Please focus on safety when driving through the construction work zone and remember, it is against the law to use a hand held cell phone while driving in Vermont.
Contact Natalie Boyle, Project Outreach Coordinator, EIV Technical Services, with any questions or concerns in regard to this project at 802-855-3893 or nboyle@eivtech.com

--
Natalie Boyle
Director of Communications

EIV Technical Services
The City Lights Building
106 East Allen St., Unit 506
Winooski, VT 05404

cell:  802.855.3893
office: 802.497.3653 ext.1037

No comments:

Spring Thoughts and Trials

 I heard the first frogs of the season on Tuesday. I was working on getting my porch set up ready for summer weather and realized there were...