Proposed Work Schedule, Week of 8/13/18, Cabot-Danville US 2 Reconstruction [Cabot-Danville FEGC F 028-3(36) C/2]
Project Location: The
1.4 mile project extends along US 2 from Last Road to Danville Hill
Road in Cabot. This is a multi-year project with most of the work
occurring in 2017/2018. Completion is scheduled for 2019.
Work
to be performed includes reconstruction, realignment and widening of a
portion of US Route 2 including bridge replacement, grading, drainage,
sub-base, pavement and other highway related items.
Installation of select roadway materials and pipe crossing will continue to take place from the Folsom Farm to Last Road has been completed.
Crews
are paving today between Folsom Farm and the Goodrich sugar house.
Traffic will be switched over to a temporary roadway at this location.
Motorists are advised that a new traffic pattern is in place from the Folsom Farm to the Goodrich property.
TRAVEL ALERT:
Motorists are advised that a traffic pattern change will be in effect
at the temporary bridge, and the existing bridge will be closed. A speed
limit reduction to 35 mph will be in effect at the location of the
temporary bridge. The remainder of the project remains at the 40 mph
speed reduction. There are increased fines for speed violations within
the construction zone.
TRAFFIC INFORMATION:
Construction vehicles will be entering and exiting the work zone
throughout construction hours, and as a result, alternating one-way
traffic patterns with flaggers will be in place. Brief delays can be
expected.
Traffic pattern change and speed reduction to 35 mph from Last Road to Folsom Farm is in effect. Traffic will be using the temporary bridge that was previously installed.
Installation of select roadway materials and pipe crossing will continue to take place from the Folsom Farm to Last Road has been completed.
Motorists are advised that a new traffic pattern is in place from the Folsom Farm to the Goodrich property.
Earthwork will begin next week at Last Rd., and b
ridge work will continue
at this location as well
.
Please
focus on safety when driving through the construction work zone and
remember, it is against the law to use a hand held cell phone while
driving in Vermont.
Contact
Natalie Boyle, Project Outreach Coordinator, EIV Technical Services,
with any questions or concerns in regard to this project at 802-855-3893
or nboyle@eivtech.com
--
Natalie Boyle
Director of Communications
EIV Technical Services
The City Lights Building
106 East Allen St., Unit 506
Winooski, VT 05404
cell: 802.855.3893
office: 802.497.3653 ext.1037
No comments:
Post a Comment