Construction Update
Cabot Danville US 2 Reconstruction
Cabot Danville US 2 Reconstruction
FEGC F 028-3(26) C/2
Project Location:
The 1.4 mile project extends along US 2 from Last Road to Danville Hill
Road in Cabot. This is a multi-year project with most of the work
occurring in 2017/2018. Completion is scheduled
for 2019.
Reduced Speed Limit – The posted speed limit has been
reduced to 40 mph through the project. Please reduce speed and use caution traveling through the construction zone.
Expect traffic delays as there will be several
active operations throughout the project.
Week of May 28, 2018
Crews
will be off the road by noon on Friday, 5/25/18 in observance of the
Memorial Day holiday. Work will resume on Tuesday, 5/29/18.
Crews
will be working on the approaches to the temporary bridge west of
Houghton Road.
Crews
are scheduled to continue road widening operations throughout the week of
5/28. This work will occur at Houghton Rd. and progress toward
the Folsom Farm.
Construction of the retaining
wall in front of the Goodrich Farm will continue throughout the week of 5/28.
Installation of dense grade crush stone and sand borrow material will continue from Danville Hill Rd. to the Goodrich property.
Construction vehicles will be entering and exiting the work zone
throughout construction hours, and as a result, alternating one way
traffic patterns with flaggers will be in place. Brief delays can be
expected.
Contact
Natalie Boyle, Project Outreach Coordinator, EIV Technical Services,
with any questions or concerns in regard to this project at
802-855-3893 or nboyle@eivtech.com.
--
Natalie Boyle
Director of Communications
EIV Technical Services
The City Lights Building
106 East Allen St., Unit 506
Winooski, VT 05404
off: 802.497.3653
cell: 802.855.3893