BRIDGE 83 ON VT 15 IS CLOSED TO ALL TRAFFIC.  THE DETOUR BELOW IS IN EFFECT UNTIL THE BRIDGE IS REOPENED. 
Detour -
A traffic detour is in effect and marked with directional signs. 
·         Motorists wanting to travel to Hardwick on VT 15 from US 2 West will continue on US 2 West to VT 215 in Marshfield and follow VT 215 to VT 15 in Walden.
·         Motorists traveling from VT 15 in Walden to US 2 East will take VT 215 to Marshfield to US 2 East.
 
Saturday (7/25) and Sunday (7/26) - Crews are planning to work on the roadway excavation and installation of the crushed gravel subbase.  Work will also include stonefill slope work and setting the approach slabs.
   
Week of July 27th, 2105

Construction Progress – Week of July 20th, 2015 - Crews set abutment #2 and the NEXT beams.  Photo – At right is a photo of the crews setting the NEXT beams.
Week of July 27th – Crews will be applying the bridge membrane, installing guardrail, paving and line striping.  The project is on schedule. 


Traffic delays are expected during the closure period while the detour is in effect. Motorists are encouraged to allow for extra time and plan accordingly.
 
Contact Francine Perkins, Project Outreach Coordinator, at 802-479-6994 with questions.  Visit www.roadworkupdates.com to view the most recent updates for the project.