Work Update
Walden Bridge Replacement –VT 15
Walden BRF030-3 (5)
Walden Bridge Replacement –VT 15
Walden BRF030-3 (5)
Project Location: Bridge 83 is located over Joe’s Brook approximately 5 miles southeasterly of the Hardwick/Walden town line. Project will include an allowable 28-day bridge closure period within the timeframe of June 22, 2015 and August 21st, 2015. Completion is scheduled for October 2015.
Bridge Closure Period – The contractor has scheduled the 28-day bridge closure period to begin on July 6th and end on August 2, 2015.
Detour - During
the bridge closure period, a traffic detour will be in effect and
marked with directional signs. Motorists wanting to travel to Hardwick
on VT 15 from US 2 West will continue on US 2 West to VT 215 Marshfield
and follow VT 215 to VT 15 in Walden. Motorists traveling from VT 15 in
Walden to US 2 East will take VT 215 to Marshfield to US 2 East.
Week of June 29th, 2015
Independence Day Work Hours – With
the upcoming holiday weekend, crews will not be working on the project
from the afternoon of Thursday, July 2, 2015 thru Sunday, July 5th. Work will resume on the project Monday, July 6th, 2015.
Crews will be setting up a platform under the bridge to contain the concrete debris during demolition. Traffic will be reduced to alternating one-way traffic with flaggers present to assist in maintaining traffic flow.
Traffic – Minor traffic delays are expected this week.
Crews will be setting up a platform under the bridge to contain the concrete debris during demolition. Traffic will be reduced to alternating one-way traffic with flaggers present to assist in maintaining traffic flow.
Traffic – Minor traffic delays are expected this week.
It
is illegal in VT to use any handheld portable electronic devices while
driving. The law carries fines of up to $200 with points assessed if the
violation occurs in a work zone.
Contact Francine Perkins, Project Outreach Coordinator, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994 or for a more up-to-date schedule visit www.roadworkupdates.com.
Contact Francine Perkins, Project Outreach Coordinator, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994 or for a more up-to-date schedule visit www.roadworkupdates.com.