Friday, August 16, 2013

Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)

WEEK OF 8/19/13

Work this week will include:
The sidewalk work that was scheduled to start last Monday was postponed until Wednesday so crews will continue with the work through this week.
  • Sidewalk work will continue throughout the week on Park Street to the Library and also around the Bandstand. 
  • Crews will continue installing concrete steps at a residence on Route 2 next to the Diamond Hill Store.  This work will require alternating one-way traffic at various times later in the week when the concrete is being poured. 

New traffic signals still need to be installed at the Route 2/Peacham/Hill intersection.  This work is in the process of being scheduled to take place within the next few weeks.  Traffic will be impacted by this work.  More details will be released once they become available. 

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Thanksgiving Wishes!

Happy Thanksgiving to all of you! I am always thankful for so many who read my blog, and I think most of us have a lot to be thankful for - ...