Work
Update
Danville
Route 2 Project
Project: Danville FEGC
028-3(32)
Paving
Update
Monday, 6/24/13
Monday, 6/24/13
PAVING:
As
of 3:00pm, crews had paved one lift of asphalt on the streets that surround the
Village Green and some on Hill Street. They were on hold because of a
severe thunderstorm going through Barre where the asphalt plant is located. The weather will dictate if they
continue paving today.
The
paving plan for tomorrow is to finish the second lift around the Village Green
and Hill Street and start on Route 2.
Paving of Route 2 will probably continue into Wednesday.
PAVING
TRAFFIC DELAYS –
Travel will be reduced to alternating
one-way traffic in the center of Town while crews are paving. Motorists should expect and plan for
traffic delays when traveling in and around the project.
Contact
Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any
questions or concerns with regard to this project at 802-479-6994 or for a more
up to date schedule visit www.roadworkupdates.com.