Monday, June 24, 2013

Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)

Paving Update
Monday, 6/24/13
PAVING:
As of 3:00pm, crews had paved one lift of asphalt on the streets that surround the Village Green and some on Hill Street.   They were on hold because of a severe thunderstorm going through Barre where the asphalt plant is located.  The weather will dictate if they continue paving today.
The paving plan for tomorrow is to finish the second lift around the Village Green and Hill Street and start on Route 2.  Paving of Route 2 will probably continue into Wednesday. 
PAVING TRAFFIC DELAYS Travel will be reduced to alternating one-way traffic in the center of Town while crews are paving.  Motorists should expect and plan for traffic delays when traveling in and around the project.
Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.