Friday, June 21, 2013

Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)

WEEK OF 6/24/13
PAVING:
Final wearing course paving in the center of Town is set to start on Monday and last into Wednesday. Below is the tentative schedule for paving:
Monday – Weather permitting – Crews plan to pave the streets around the Village Green (Park, Smith and Peacham) and also Hill Street.
Tuesday – Weather permitting – Crews plan to pave Route 2 and tie in the side roads.
Wednesday – Weather permitting – crews plan to pave in driveway aprons, side road entrances and parking lot entrances.
If it rains, paving will be canceled and rescheduled for another time.
PAVING TRAFFIC DELAYS Travel will be reduced to alternating one-way traffic in the center of Town while crews are paving.  Motorists should expect and plan for traffic delays when traveling in and around the project.
Landscaping will be installed in the Village Green throughout the week.
Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.