Work
Update
Danville
Route 2 Project
Project: Danville FEGC
028-3(32)
Friday,
June 7, 2013
Crews
are coming in today to mill on Route 2 in anticipation of final wearing course
paving. Milling will take place at
the joints where the new pavement meets the pavement placed last fall. This work will reduce travel to
alternating one-way on Route 2 throughout the day.
WEEK
OF 6/10/13
ROUTE
2 – Crews
will finish up curb installation along Route 2 in the center of Town.
SIDEWALK
– Crews will be installing new sidewalks throughout the project all week.
Two-way
traffic will be maintained as much as possible. However, Route 2 may be reduced to alternating
one-way traffic in the center of Town at various times during the week. Motorists should expect and plan for
traffic delays when traveling in and around the project.
Contact
Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any
questions or concerns with regard to this project at 802-479-6994 or for a more
up to date schedule visit www.roadworkupdates.com.
* * * * *