WEEK OF 4/19/13
Work this week will shift from pipe installation to roadway reconstruction in the middle of town. 
PEACHAM ROAD CLOSURE – Peacham Road will be closed between Route 2 and Park Street Monday, April 22nd from 8:00 am thru the end of the day.  Traffic control personnel will be present to maintain traffic flow.
ROUTE 2 - Route 2 will be reduced to alternating one-way traffic at various times this week while crews reclaim and widen the existing roadway.  Traffic control personnel will be present to maintain traffic flow.
Box cut will start on Route 2 on Thursday, April 25th at Melody Hill and progress west.  This work will include the removal of the current aggregate material under the roadway and replacement of new aggregate material.  Crews are planning for two-way traffic during this work.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.