Work Update
Danville
Route 2 Project
Project: Danville FEGC
028-3(32)
WEEK
OF 10/29/12
Village
Green:
UTILITY
CREWS – Crews from FairPoint and Charter will be working for the next few months
to relocate their lines underground.
Route
2:
Street
Lights: Crews will continue working
on the new street lighting along Route 2 this week.
Line
Striping: There are two remaining
crosswalks to be installed, both on Route 2. This work is contingent upon favorable
weather conditions.
Line
striping will require lane closures and alternating one-way traffic throughout
the project. Traffic control
personnel will be present to maintain traffic flow.
Crews
will be sealing structures along Route 2, weather permitting.
Contact
Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any
questions or concerns with regard to this project at 802-479-6994 or for a more
up to date schedule visit www.roadworkupdates.com.