Friday, October 26, 2012




 

Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)

WEEK OF 10/29/12
 Village Green:

UTILITY CREWS – Crews from FairPoint and Charter will be working for the next few months to relocate their lines underground. 

Route 2:

Street Lights:  Crews will continue working on the new street lighting along Route 2 this week. 

Line Striping:  There are two remaining crosswalks to be installed, both on Route 2.  This work is contingent upon favorable weather conditions. 

Line striping will require lane closures and alternating one-way traffic throughout the project.  Traffic control personnel will be present to maintain traffic flow.

Crews will be sealing structures along Route 2, weather permitting. 


Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Busy Week Ahead!

 This will be a very busy week with the Fourth of July activities and every community in the north country having picnics, parades, and fest...