Work
Update
Danville
Route 2 Project
Project: Danville FEGC
028-3(32)
WEEK
OF 9/24/12
(Including 9/23/12)
(Including 9/23/12)
Village
Green:
UTILITY
CREWS – Crews from FairPoint and Charter will be working for the next few months
to relocate their lines underground.
Route
2:
PAVING: Weather permitting, crews will be paving
all day Sunday 9/23/12 through midnight-12:00 am.
The
plan for paving is for crews to start prep work (driveways, etc) around 10:00 am
with paving to start at 12:00 pm-Noon.
Paving is scheduled to begin on the west end of the project and continue
east towards Marty’s.
Motorists
can expect alternating one-way traffic through the construction zone. Traffic control personnel will be
present to maintain traffic flow.
If
it rains and the shift is cancelled on Sunday, 9/23/12– crews will work Monday,
September 24th from 6:00 pm to 6:00
am.
Wednesday,
crews will be adjusting structures along Route 2 in preparation for paving on
Sunday, 9/30/12.
PAVING: Sunday, September 30th, 2012
– All day through 12:00 am
If
it rains and the shift is cancelled – crews will work Monday, September
31st from 6:00 pm to 6:00 am.
Contact
Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any
questions or concerns with regard to this project at 802-479-6994 or for a more
up to date schedule visit www.roadworkupdates.com.