WEEK OF 9/24/12
(Including 9/23/12)
Village Green:

UTILITY CREWS – Crews from FairPoint and Charter will be working for the next few months to relocate their lines underground. 
 
Route 2:

PAVING:  Weather permitting, crews will be paving all day Sunday 9/23/12 through midnight-12:00 am. 

The plan for paving is for crews to start prep work (driveways, etc) around 10:00 am with paving to start at 12:00 pm-Noon.  Paving is scheduled to begin on the west end of the project and continue east towards Marty’s.

Motorists can expect alternating one-way traffic through the construction zone.  Traffic control personnel will be present to maintain traffic flow.

If it rains and the shift is cancelled on Sunday, 9/23/12– crews will work Monday, September 24th from 6:00 pm to 6:00 am.

Wednesday, crews will be adjusting structures along Route 2 in preparation for paving on Sunday, 9/30/12.


PAVING:  Sunday, September 30th, 2012 – All day through 12:00 am
If it rains and the shift is cancelled – crews will work Monday, September 31st from 6:00 pm to 6:00 am.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Spring Weather/Good News

 Thank goodness we have a rainy day today! Yesterday was so nice I was outside probably more than my winter-weary body needed, so today I...