Friday, September 14, 2012

Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)

WEEK OF 9/17/12
Village Green:

UTILITY CREWS – Crews from FairPoint and Charter will be working for the next few months to relocate their lines underground. 
 
Route 2:

Landscaping crews will be installing trees along Route 2. 

Crews will be installing new traffic signs throughout the project.

PAVING:  Crews will be paving the final layer of pavement on the east and west ends of the project the following days/nights:

Sunday, September 23rd, 2012 – All day through 12:00 am
If it rains and the shift is cancelled – crews will work Monday, September 24th from 6:00 pm to 6:00 am.

Sunday, September 30th, 2012 – All day through 12:00 am
If it rains and the shift is cancelled – crews will work Monday, September 31st from 6:00 pm to 6:00 am.

A confirmed paving plan will be issued next week.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Another Adventure

This week turned out to be a doozie for me. I had anticipated going for a follow-up on my knee on Monday, but instead ended up in the ER at ...