Project: Danville FEGC
028-3(32)
WEEK
OF 7/9/12
ROUTE
2 ROAD WORK
East
End of Project:
Crews
will be installing street light bases along Route 2 between Melody Hill and
Marty’s. Travel will remain two-way
while this work is performed.
West
End of Project:
Crews
will install new sidewalks beginning at Passumpsic Bank and continuing west
along the south side of Route 2.
Travel will remain two-way while this work is
performed.
Village
Green:
Crews
will perform miscellaneous clean-up work around the Green in anticipation of
paving.
Travel
will be reduced to alternating one-way traffic around the construction
zone. Traffic control will be
present to maintain traffic flow.
Motorists may experience delays.
Contact
Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any
questions or concerns with regard to this project at 802-479-6994 or for a more
up to date schedule visit www.roadworkupdates.com.