Friday, July 06, 2012

Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)

WEEK OF 7/9/12
 ROUTE 2 ROAD WORK

East End of Project: 

Crews will be installing street light bases along Route 2 between Melody Hill and Marty’s.  Travel will remain two-way while this work is performed.

West End of Project:

Crews will install new sidewalks beginning at Passumpsic Bank and continuing west along the south side of Route 2.  Travel will remain two-way while this work is performed.

Village Green:

Crews will perform miscellaneous clean-up work around the Green in anticipation of paving.  

Travel will be reduced to alternating one-way traffic around the construction zone.  Traffic control will be present to maintain traffic flow.  Motorists may experience delays.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.