Work
Update
Danville
Route 2 Project
Project: Danville FEGC
028-3(32)
Week of 6-25-12
ROUTE
2 ROAD WORK
East
End of Project:
BOX
CUT – Early week, crews will continue to work on the box cut working their way
west on Route 2.
FINE
GRADE AND PAVE – Once the box cut work is finished, possibly mid week, crews
will fine grade the east end of the project followed by paving of the base
course. A mid-week update will be
issued as to the work plan for mid-late week.
VILLAGE
GREEN -
CVPS
will be running wire to residences around the Village Green all week.
Travel will be reduced to alternating
one-way traffic around the construction zone. Traffic control will be present to
maintain traffic flow. Motorists
may experience delays.