Project:  Danville FEGC 028-3(32)

WEEK OF 6/4/12

Route 2 Roadwork:

West End of Project:  Crews will continue fine grading the unpaved roadway an anticipation of paving.   Paving may take place mid week. 

East End of Project:  Crews will begin the box cut on the east end of the project starting at Marty’s and working their way towards the center of Town.  This work will require alternating one-way traffic around the construction zone. 

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.