
Work Update
Danville Route 2 Project
Project: Danville FEGC 028-3(32)
WEEK OF 4/9/12
The work plan for this week will have crews concentrating on the West end of the project between the Danville School and the end of the project.
Crews will be installing drainage pipe between the school and the end of the project. This work will require alternating one-way traffic around the work zone.
Crews will also be building slopes off of Route 2 near the school. Although the work will occur off Route 2, trucks entering and exiting the off road work site will have a minor impact on Route 2 traffic.
The Village Green will have light construction activity throughout the week. Trucks will be entering and exiting the area to stockpile material for the upcoming road work.
Work hours will be daylight hours until further notice.
Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.
No comments:
Post a Comment