Friday, October 28, 2011

Work Update

Danville Route 2 Project

Project: Danville FEGC 028-3(32)

WEEK OF 10/31/11

NIGHT WORK:

No night work is planned for next week.

DAY WORK:

WATER LINE SERVICES- work on water services will continue along Route 2 between Mountainview Drive and the Danville School throughout the week.

DUCT BANK - Crews will work on installing duct banks in and around the Village Green.

STORM DRAIN – Crews will work on storm drain in and around the Village Green.

ROAD WORK – In anticipation of paving Route 2, crews will be grading the roadway between Park Street and the Danville School. Crews will also be adjusting the height of catch basins so they will match the height of the new pavement.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.