Friday, September 23, 2011

Work Update

Danville Route 2 Project

Project: Danville FEGC 028-3(32)

WEEK OF 9/26/11

NIGHT WORK

Water line and drainage installation will continue on Route 2 from Mountainview Drive towards the school throughout the week.

Crews will also be working on Route 2 near the school installing new sewer lines throughout the week.

Motorists can expect alternating one-way traffic within the work zone. Traffic control will be present to maintain traffic flow.

DAY WORK

BLASTING – Due to difficulty breaking up the ledge by the school with the drills and excavators, crews may be blasting on Route 2 during the week. More details will follow regarding dates and times.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Cold & Snowy

 We've had such a mix of weather in the past several days, it's really hard to keep up. I've had to check the thermometer before...