Friday, August 26, 2011

Work Update

Danville Route 2 Project

Project: Danville FEGC 028-3(32)

WEEK OF AUGUST 29th, 2011

Pike Industries will continue work on the Danville Route 2 project as follows:

All work for Monday is contingent on favorable weather. If work is cancelled Monday the work plan will be adjusted to reflect work starting Tuesday instead of Monday.

Blasting: Crews expect to finish blasting near the post office on Park and Peacham Road Friday 8/26/11, however, if this work is not completed as expected, blasting will continue on Monday 8/29/11.

Rock drilling is scheduled Monday and Tuesday at the corner of Park Street and Route 2.

Wednesday through the end of the week, ledge excavation and rock drilling will take place on Route 2 from the Town Hall east to Walden Hill Road.

Crews will be working on Water line installation from Park Street to Walden Hill Road on Route 2 Wednesday and Thursday.

Ditching and clean-up will take place between Marty’s and Highland Ave throughout the week. This work will allow for two-way traffic.

In observance of the Labor Day holiday weekend, crews will stop working on Friday, September 2nd, 2011 at 12:00 pm and will not return to work until Tuesday, September 6th.

Motorists can expect traffic delays from the alternating one-way traffic around the construction zone. Traffic control will be present to maintain traffic flow. Motorists are encouraged to plan accordingly for delays.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Regulations and Seasonal Changes

 The change to Vermont's boating regulations regarding wake boats went into effect on April 15. One of the new regulations I wasn't...