Project: Danville FEGC 028-3(32)

Week of May 30th, 2011

Pike Industries will be performing the following work on the Danville Route 2 project as follows:

Due to the holiday weekend, crews will not return to work until Tuesday morning, May 31st at 8 am.

Building of the new sediment pond across from Marty’s Store will continue. This work will have minimal impact, if any, on traffic flow.

Tree cutting around the Green will also continue. This work should have no impact on traffic.

Waterline work will continue between Marty’s and Peacham Road in the westbound lane of Route 2. The work will remain centered in this area for most of the week. If time allows, crews will then start working their west on Route 2 towards the center of Town. This work will require lane closures.

Probing for ledge along Route 2 between Peacham Road and the High School in both eastbound and westbound lanes is expected to be completed by the end of the day Tuesday. This work will require lane closures as well.

Blasting may occur towards the end of the week between Peacham Road and the High School in the westbound lane. More details will be released as soon as possible if this work is confirmed in the work schedule.

All work this week will start at 8 am each day.

Traffic delays can be expected in and around the project for the entire week. Traffic control will be present to maintain traffic flow at all times. Motorists are encouraged to plan accordingly.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Spring Thoughts and Trials

 I heard the first frogs of the season on Tuesday. I was working on getting my porch set up ready for summer weather and realized there were...