Construction Update
Cabot Danville US 2 Reconstruction
FEGC F 028-3(26) C/2
  
Project Location:  The 1.4 mile project extends along US 2 from Last Road to Danville Hill Road in Cabot. This is a multi-year project with most of the work occurring in 2017/2018. Completion is scheduled for 2019.

 
December 11th thru December 21st, 2017
 
For the next few weeks, most of the work will occur east of Goodrich’s Maple Farm as described below.

If weather and schedules allow, additional work may include preparation work for the retaining wall at Goodrich’s Maple Farm and upland ditching west of Folsom Farm to Houghton Road.  


The next construction update will be issued December 21st, 2017.

US 2 – East (Danville Side) of Goodrich’s Maple Farm

Crews will continue construction on the second phase of excavation for the new roadway alignment east of Goodrich’s Maple Farm.  Work will include installing new underdrain and select stone material.  Short traffic interruptions may occur to allow for trucks to enter and exit the construction site.

Excavation for the retaining wall at Goodrich’s Farm will continue this week also.

* Trucks will be hauling material to the fill area near the Folsom Farm throughout the week which could result in minor traffic interruptions as trucks access the area.

Traffic – Minor traffic delays can be expected throughout December.

It is illegal in VT to use any handheld portable electronic devices while driving. The law carries fines of up to $200 with points assessed if the violation occurs in a work zone. 

Contact Francine Perkins, Project Outreach Coordinator, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994.  Construction updates are posted at www.roadworkupdates.com