Saturday, September 01, 2012

Work Update
Danville Route 2 Project
Project:  Danville FEGC 028-3(32)

WEEK OF 9/3/12

Crews will not be working Monday, 9/3/12, in observation of Labor Day.  Work on the project will resume Tuesday, 9/4/12.

Village Green:

UTILITY CREWS – Crews from FairPoint and Charter will be working for the next few months to relocate their lines underground. 

Crews will finish installing new sidewalk around the Park and continue constructing the stone wall throughout the week.


Route 2:

Crews will be installing artistic enhancements and new landscape plantings throughout the project.

Miscellaneous clean-up work will also be performed throughout the project.


Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.