Work
Update
Danville
Route 2 Project
Project: Danville FEGC
028-3(32)
WEEK
OF 9/3/12
Crews
will not be working Monday, 9/3/12, in observation of Labor Day. Work on the project will resume Tuesday,
9/4/12.
Village
Green:
UTILITY
CREWS – Crews from FairPoint and Charter will be working for the next few months
to relocate their lines underground.
Crews
will finish installing new sidewalk around the Park and continue constructing
the stone wall throughout the week.
Route
2:
Crews
will be installing artistic enhancements and new landscape plantings throughout
the project.
Miscellaneous
clean-up work will also be performed throughout the
project.
Contact
Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any
questions or concerns with regard to this project at 802-479-6994 or for a more
up to date schedule visit www.roadworkupdates.com.