Danville Route 2 Project
Project:  Danville FEGC 028-3(32)
WEEK OF 8/6/12

Village Green:

ELECTRICAL SERVICES – Utility crews will be connecting new underground electrical services to businesses and residences around the Green for the next two weeks.  This work will require power interruptions for 2-4 hours at a time.  Notices will be provided regarding power interruptions.


Route 2:

Miscellaneous clean-up work will be performed throughout the project.


Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.