Friday, July 29, 2011


Work Update

Danville Route 2 Project

Project: Danville FEGC 028-3(32)

WEEK OF AUGUST 1ST, 2011


ROUTE 2- Crews will continue installing water line and storm drainage along Route 2 between Marty’s and the center of Town.

Work hours during the week on Route 2 are from 9am to 4 pm. No weekend work is scheduled at this time.

Smith Street: Crews will be installing water line on Smith Street throughout the week.

Motorists will encounter traffic delays with regard to the work on Route 2 and Smith Street. Traffic control will be present to maintain traffic flow in these areas. Motorists are encouraged to plan accordingly for delays.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Regulations and Seasonal Changes

 The change to Vermont's boating regulations regarding wake boats went into effect on April 15. One of the new regulations I wasn't...