Work Update
Danville Route 2 Project
Project: Danville FEGC 028-3(32)
Week of June 6th, 2011
Pike Industries will be performing the following work on the Danville Route 2 project as follows:
Building of the new sediment pond across from Marty’s Store will continue. This work will have minimal impact, if any, on traffic flow.
Waterline work will continue between Highland Ave and Smith Street in the westbound lane of Route 2. The work will remain centered in this area for most of the week. If time allows, crews will work on installing waterline on Smith Street. This work will require lane closures.
Blasting may occur starting Wednesday between Peacham Road and the High School in the westbound lane. More details about the exact time, location and traffic delays associated with the blasting will be released as soon as possible if this work is confirmed in the work schedule.
Starting Thursday, reclamation of the existing roadway on Route 2 will occur from Park Street to the project limit west of the Danville School. This work will require lane closures.
All work this week will start at 8 am each day.
Traffic delays can be expected in and around the project for the entire week. Traffic control will be present to maintain traffic flow at all times. Motorists are encouraged to plan accordingly.
Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regard to this project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.