Bridge and Trail Opening Notice
St. Johnsbury VT 2B – Bridge Project
St. Johnsbury VT 2B – Bridge Project
BF 7000(20)
Project Location:
Bridge 6 is located on VT 2B in St. Johnsbury over the Lamoille Valley
Rail Trail. The bridge is less than one half mile west of Route 2B’s
eastern intersection with US Route 2.
Saturday, June 24, 2017
As
of 9:00 pm this evening, Bridge 6 on VT 2B and the Lamoille Valley Rail
Trail re-opened to traffic. The 50-day bridge closure and estimated
28-day trail closure started on May 10th, 2017. Although the rail trail opening was delayed due to continued overhead work, the bridge re-opened in 45 days.
The offsite traffic and trail detours are no longer in effect.
Next week, restoration of the staging area on VT 2B and miscellaneous clean-up activities will continue through the week.
It
is illegal in VT to use any handheld portable electronic devices while
driving. The law carries fines of up to $200 with points assessed if the
violation occurs in a work zone.
Contact Francine Perkins, Project Outreach Coordinator, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994. Construction updates and project photos are posted at http://stj2bbridge.vtransprojects.vermont.gov/index.html
Francine Perkins
Project Outreach Coordinator
FRP Enterprises, LLC