Construction Update
Cabot Danville US 2 Reconstruction FEGC F 028-3(26) C/2 Project Location: The 1.4 mile project extends along US 2 from Last Road to Danville Hill Road in Cabot. This is a multi-year project with most of the work occurring in 2017/2018. Completion is scheduled for 2019.
Reduced
Speed Limit – The posted speed limit has been reduced to 40 mph through
the project. Please reduce speed and use caution traveling through the
construction zone.
Week of August 14th, 2017
Work
will start on the project this week with the installation of
construction signs and environmental controls. If the schedule allows,
towards the end of the week, crews may begin heavy excavation on the
east end of the project near Danville Hill Road.
Traffic – Most of the work this week will require intermittent traffic interruptions. Short traffic delays can be expected. It is illegal in VT to use any handheld portable electronic devices while driving. The law carries fines of up to $200 with points assessed if the violation occurs in a work zone. Contact Francine Perkins, Project Outreach Coordinator, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994. Construction updates and project photos are posted at www.roadworkupdates.com |
Thursday, August 10, 2017
Subscribe to:
Post Comments (Atom)
AND THE WINNER IS . . . !
The winner of the 2024 Joe's Pond Ice-Out Contest is Stuart Ramsdell of Danville. Stuart is retired and bought five tickets at Hastings ...
-
Another spring day and again we've had a bit of everything. Not much sunshine, but the temperature got well into high 50s. On the news...
-
Most of Vermont is struggling this morning, either cleaning up after high water damage or trying to "get there from here." Roads a...
-
This may be one of the last ice reports we will be able to give to you. The weather is going to remain warm, so conditions are changing quic...
No comments:
Post a Comment