Thursday, November 16, 2017

Construction Update
Cabot Danville US 2 Reconstruction
FEGC F 028-3(26) C/2
  
Project Location:  The 1.4 mile project extends along US 2 from Last Road to Danville Hill Road in Cabot. This is a multi-year project with most of the work occurring in 2017/2018. Completion is scheduled for 2019.

Thanksgiving Holiday Break:  No work will be performed on the project from Wednesday afternoon (11/22) through Sunday (11/26).  Work will resume on Monday (11/27).

 
 
Week of November 20th, 2017
 
     Construction will be occurring in several areas within the project limits this week.  A majority of the work this week will occur east of Goodrich’s Maple Farm.
      Minor work will be performed on the temporary roadway approaches for the temporary bridge that will be placed over Molly’s Brook just south of Last Road.  Traffic can expect minor interruptions.

US 2 – East (Danville Side) of Goodrich’s Maple Farm
       Crews will continue construction on the second phase of excavation for the new roadway alignment east of Goodrich’s Maple Farm.  Work will include installing new underdrain and select stone material.
      Crews will be excavating to tie in the existing roadway to the new roadway alignment which is under construction.

* Trucks will be hauling material to the fill area near the Folsom Farm throughout the week which could result in minor traffic interruptions as trucks access the area.
      Alternating one-way traffic will be maintained for the construction package east of Goodrich’s Maple Farm. Expect short delays.  

US 2 Bridge #88 (Near Folsom Farm) Replacement:  
      Work on the bridge will be wrapping up for the winter this week.  Crews will resume work on the bridge in the spring of 2018.

Traffic – Minor traffic delays can be expected this week.

It is illegal in VT to use any handheld portable electronic devices while driving. The law carries fines of up to $200 with points assessed if the violation occurs in a work zone. 

Contact Francine Perkins, Project Outreach Coordinator, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994.  Construction updates are posted at www.roadworkupdates.com
 
 

No comments:

AND THE WINNER IS . . . !

The winner of the 2024 Joe's Pond Ice-Out Contest is Stuart Ramsdell of Danville. Stuart is retired and bought five tickets at Hastings ...